Friday, July 1, 2016

General Site Clean-Up and Asphalt Patching Performed.

Work Completed Last Week, June 27th to July 1st  
·         Limited work completed on-site
·         Internal televising of storm sewer and sanitary sewer
·         Patching of roadway at Sunset Ridge Road and Maple Lane
·         General site clean-up

Work Anticipated to be completed Next week, July 4th to July 8th  
·         No work over the July 4th Holiday
·         Installation and final grading of topsoil

The contractor is scheduled to begin grading and installing topsoil next week.

The sod installation and asphalt driveway restorations will be performed following the paving of the final asphalt surface. Currently the asphalt surface paving is scheduled of the week of July 11th.

The contractor will not be on-site over the July 4th Holiday. Have a safe and enjoyable Holiday Weekend!!!